Facilities Update
Building – Facilities update 13 05 19
Works completed this week:
- Synthetic Grass
- Air conditioner condenser unit installation
- Internal/external complexing works
- Suspended ceiling
- Epoxy flooring to first floor veranda
- Carpet installation
Works underway from next week:
- Lift commissioning
- Final commissioning of power, data and security
- Under battening to building perimeter and stairs
- Stairs access to the oval
- Final commission of air conditioners
- Fit perforated screens
- Final Clean
- Final painting touch ups
Keys dates for building delivery and hand over:
Planned completion date for BAC and PC inspection for hand over – Week commencing 20/05