Facilities Update - Demountable Project
Key Dates for Commencement of Site Works:
- Monday 01/04
- Excavation works for pit and pipe for power.)
- Wednesday 03/04
- Commence footing excavation and subfloor steel work
- Friday 12/04
- Planned building delivery and installation
Proposed -Keys dates for building delivery and hand over:
Complex and weather proof modules 12/04
Install suspended ceiling – Week commencing 15/04
Internal Complexing joins – Week commencing 15/04
Internal looping of power, data and security between modules – Week commencing 15/04
Connect and commission power, data and security – Week commencing 22/04
Commission air conditioners – Week commencing 29/04
Carpet installation – Week commencing 29/04
Final clean and painting touch ups internal/external – Week commencing 06/05
Planned completion date for BAC and PC inspection for hand over – Week commencing 06/05