Construction Status and Progress of Works
- Site establishment has been completed with erection of temporary fencing, hoardings and sediment controls
- Site works have commenced with initial stripping of external areas, some tree removal and demolition of fencing and outdoor structures, etc.
- Services (power, water & gas) have been disconnected to Annie St houses.
- Site Clearing – 80%completed
- Installation of temporary power to the site- 100%completed.